construction Project updates

Phase-2: September Update – 1

During last week, erection of beam between col. 4B and 4C along with perimeter angle for the roof was completed. Roof deck was also finished. Water service was brought into the mechanical room .Storm drain at northern property and roof frames were setup as well.

Phase-2: July Update – 1

Construction Update: July 5th

Due to long weekend, there was minimal activity on the construction front to report this week. In the current structure, the openings for skylight all the way up three stories is clearly visible. We can literally feel and comprehend the actual size of this magnificent temple, which is breathtaking.  More updates are coming soon.

LATEST PROJECT STATUS

PHASE-1 | COMPLETED

The planned work to construct the new and expanded parking lot, parking lot lighting, and all the underground utilities (city water, sewer, gas, etc.), has been completed on time and on budget.

PHASE-2 | IN PROGRESS

We are pleased to inform you that the construction for Phase 2 of the new temple will commence on April 21, 2021! We have received all the required city approvals. Please feel free to visit our website for the latest updates.