Phase-2: September Update – 1
During last week, erection of beam between col. 4B and 4C along with perimeter angle for the roof was completed. Roof deck was also finished. Water service was brought into the mechanical room .Storm drain at northern property and roof frames were setup as well.
Phase-2: July Update – 4
Phase-2: July Update – 3
Construction Update: July 19 th
The reinforced concrete foundation for the main building is in place. Steel framing is currently in process.
Phase-2: July Update – 2
Construction Update: July 17 th
Temple construction started on Rama-navami day. Steel framing work will continue for few more weeks. Everything is moving on schedule as planned.
Phase-2: July Update – 1
Construction Update: July 5th
Due to long weekend, there was minimal activity on the construction front to report this week. In the current structure, the openings for skylight all the way up three stories is clearly visible. We can literally feel and comprehend the actual size of this magnificent temple, which is breathtaking. More updates are coming soon.
LATEST PROJECT STATUS
PHASE-1 | COMPLETED
The planned work to construct the new and expanded parking lot, parking lot lighting, and all the underground utilities (city water, sewer, gas, etc.), has been completed on time and on budget.
PHASE-2 | IN PROGRESS
We are pleased to inform you that the construction for Phase 2 of the new temple will commence on April 21, 2021! We have received all the required city approvals. Please feel free to visit our website for the latest updates.
It goes without saying that all this tremendous work requires the continued support of the community. A temple of this magnitude and purpose will undoubtedly become your legacy for many generations to come. Your gracious financial support is solicited and sincerely appreciated.