construction Project updates

Phase-2: September Update

Perimeter parapet roof studding is 85% complete. Perimeter exterior wall framing is 70% done. Underground plumbing penetrations have been finished along with steel framing for all the stairs which is 95% done.

Phase-2: September Update

Construction of our much awaited temple is progressing at a smooth pace.Currently, the elevator work is in progress. Approval of dual gas service for existing structure throughout the winter season was obtained. Perimeter parapet wall and kicker base have been completed. 

Phase-2: September Update – 1

During last week, erection of beam between col. 4B and 4C along with perimeter angle for the roof was completed. Roof deck was also finished. Water service was brought into the mechanical room .Storm drain at northern property and roof frames were setup as well.

LATEST PROJECT STATUS

PHASE-1 | COMPLETED

The planned work to construct the new and expanded parking lot, parking lot lighting, and all the underground utilities (city water, sewer, gas, etc.), has been completed on time and on budget.

PHASE-2 | IN PROGRESS

We are pleased to inform you that the construction for Phase 2 of the new temple will commence on April 21, 2021! We have received all the required city approvals. Please feel free to visit our website for the latest updates.

It goes without saying that all this tremendous work requires the continued support of the community. A temple of this magnitude and purpose will undoubtedly become your legacy for many generations to come. Your gracious financial support is solicited and sincerely appreciated.


Chase QuickPay

For Chase QuickPay or Zelle, Send your donation to :
[email protected]

Official PayPal Seal