Phase-2: September Update

Construction of our much awaited temple is progressing at a smooth pace.Currently, the elevator work is in progress. Approval of dual gas service for existing structure throughout the winter season was obtained. Perimeter parapet wall and kicker base have...

Phase-2: September Update – 1

During last week, erection of beam between col. 4B and 4C along with perimeter angle for the roof was completed. Roof deck was also finished. Water service was brought into the mechanical room .Storm drain at northern property and roof frames were setup as...